InglêsInterpretação de texto | reading comprehension
- (FCC 2014)
San Francisco Subway TBMs Dig Deep to Overcome Tunnel Challenges
September 4, 2013
By Greg Aragon
Tunneling 100 ft below a busy city with varying substructure is a delicate job, especially when the work comes ..... A .... 8 ft of existing tunnels. Such is the case on San Francisco's new $1.5-billion Central Subway Project, which began major subterranean excavation last month.
"The tunnels pass through both soft ground and Franciscan formation, which is heterogeneous rock that is not predictable except in its unpredictability," says Sarah Wilson, a San Francisco Municipal Transportation Agency (SFMTA) resident engineer.
While underground conditions will be tricky, the project's twin earth-pressure-balance tunnel-boring machines will be able to adjust their blades and cut through any sand, dirt or rock, says Wilson. The TBMs, dubbed Mom Chung and Big Alma, are each 350 ft long and weigh 750 tons.
Mom Chung was first out of the 450-ft-long launch box. Over the next 10 months, she will travel north, creating a 1.7-mile-long tunnel. Big Alma will begin digging a southbound parallel tunnel later this month.
The tunnels are the main component of the Central Subway Project, which is extending the Muni Metro T Third Line through one of the most densely populated neighborhoods in the U.S. with three new underground stations and one at street level. Work on the line is scheduled to wrap up in 2019.
To prevent and control ground and adjacent structure settlement, the team will use compensation grouting, in which a horizontal array of grout pipes is installed into a shaft drilled down next to the tunnel alignment. "We are basically preconditioning the ground and making it homogeneous so that there are no surprises for the crossing," says John Funghi, SFMTA program director.
(Adapted from http://enr.construction.com/products/equipment-
Segundo o texto,
A) o tipo de solo da região não apresentará problemas para a escavação dos túneis.
B) as duas máquinas tuneladoras tiveram um custo de 1.5 bilhão de dólares.
C) a escavação do túnel começou em agosto de 2013.
D) a máquina Big Alma não tem a mesma capacidade de escavação que a Mom Chung.
E) todas as estações serão subterrâneas para minimizar o impacto na superfície.
Próximo:
EXERCÍCIOS - Exercício 323
Vamos para o Anterior: Exercício 321
Tente Este: Exercício 381
Primeiro: Exercício 1
VOLTAR ao índice: Inglês